SuperKEKB Injector Linac towards Υ(6S) Collision

[Overview] [Resonaces] [Parameters] [Schedule] [Conditioning] [Reports] [Links]


Overview


Replacing old S-band structures with newly designed structures in order to mitigate damages by discharges and to improve the gradient.

SuperKEKB injector linac employs 2-m long S-band accelerating structures (cavities). They were fabricated by using a technology called electroforming. Among them 150 structures out of 230 structures are 40 years old and have been damaged under severe operational environment. It is planned to replace some of the structures and improve the accelerating gradient to reach the collision energy up to Upsilon 6S.

Please send your comments and questions to K.Furukawa.

Resonance energies

Upsilon (Υ) states
4S : 10.5794 GeV, e+ : 4.000 GeV, e- : 7.007 GeV
5S : 10.875 GeV, e+ : 4.112 GeV, e- : 7.203 GeV
6S : 11.019 GeV, e+ : 4.166 GeV, e- : 7.298 GeV
(by t.kamitani, nov.2021 updated)
Collision energy change scenario at SuperKEKB (by y.ohnishi)

Another interesting state
10.751 GeV
10.751 GeV: e+ : 4.065 GeV, e- : 7.121 GeV
10.751 + 0.059 : 10.810 GeV: e+ : 4.087 GeV, e- : 7.160 GeV

Other parameters

Nominal energy gain per accelerating structure (2 m long)
40 MeV (20 MeV / m)
Nominal energy gain per accelerator unit (10 m long)
160 MeV
Link to
Database of accelerating structures
Beam transport line positron energy limit, QC1LP 90%, Main ring bend power supply 98%
4.290 GeV (coil heating limit, by m.kikuchi, n.tokuda, n.ohuchi)
Beam transport line electron energy limit
8.465 GeV (coil heating limit, by m.kikuchi)
Maximum (symmetric) collision energy
11.35 GeV, e+ : 4.29 GeV, e- : 7.51 GeV
Real maximum (assymmetric) collision energy
12 GeV, e+ : 4.29 GeV, e- : 8.41 GeV

Schedule

2016 - 2018.
Design and test of new accelerating structure
Summer 2020.
Conditioning of first fabrication batch
Winter 2021.
Installation of first batch at Unit #44 in Main Linac
2021c.
Beyond Y(4S) collision, energy scan at 10.66, 10.71, 10.75, 10.81 GeV, internal plan by belle2, acceleration energy confirmation by ego
2021 - 2022.
Conditioning of remaining batches of structures
Summer 2022.
Installation of an additional klystron at Unit #44 in Main Linac
Winter 2023.
Installation of structures
Winter/Spring 2023.
Beam acceleration tests (Decided in July 2022 to postpone Y(6S) to ensure more data at Y(4S))
With additional budget.
Replacement of damaged dummy loads in Main Linac, and more structures and modulators for a higher energy

Conditioning

Typical conditioning during sumer 2020.

Reports on higher-energy acceleration at the injector linac

Links

Collision energy change scenario at SuperKEKB
Database of accelerating structures (acrf)
Information of acceleration gain (epics pv)
Linac-related B2GM reports
Linac conference papers
Linac reports
Linac projects
Belle II indico


New accelerating structures at #44 unit.


[Overview] [Resonaces] [Parameters] [Schedule] [Conditioning] [Reports] [Links]


K. Furukawa <webmaster@mail-linac.kek.jp>, Linac, KEK, May.12.2020 - Oct.25.2022.
[ Linac ]   [ SuperKEKB ]   [ Belle II ]   [ Accelerator ]   [ KEK ]